The Work Breakdown Structure explained simply, with a real example and the most common mistakes to avoid.
In brief
- The WBS breaks the work down into manageable, measurable packages.
- Each package has a budget, an owner and dates.
- Three levels of detail are enough for most SMEs.
- A good WBS makes quote and actuals comparable.
What a WBS is, in plain words
The Work Breakdown Structure is a tree-shaped list of all the work needed to complete a project. You start from the end result and divide it into smaller and smaller parts, until you reach work packages that a person or a team can carry out and keep under control.
It isn’t a concept reserved for large projects: it’s the simplest way to know what needs doing, how much it should cost and where the money is going.
Step 1: start from the result to deliver
The top level of the WBS is what the customer receives: a working system, software in production, an approved detailed design. Write it down in one clear sentence.
Step 2: split it into main phases
Divide the result into 3–6 main phases. For an installation they might be design, procurement, installation and testing; for software, analysis, development, testing and release. The phases must cover all the work, with no overlaps.
Step 3: break it down into work packages
Each phase is divided into work packages. A good package has these features:
- It can be assigned to one owner.
- It has a verifiable outcome (done / not done).
- It lasts from a few days to a few weeks, not months.
- It can be estimated in hours and materials with reasonable accuracy.
Step 4: assign budget, dates and dependencies
For each package, enter planned hours, materials, external costs and start and end dates. Mark the dependencies too: testing can’t start before installation is finished. This is where the project’s Gantt chart comes from.
An example: electrical system for an industrial building
A three-level WBS might look like this:
- 1. Design: 1.1 Survey, 1.2 Wiring diagrams, 1.3 Permits and paperwork.
- 2. Procurement: 2.1 Switchboards, 2.2 Cables and cable trays, 2.3 Light fittings.
- 3. Installation: 3.1 Cable trays, 3.2 Wiring, 3.3 Switchboard assembly.
- 4. Testing: 4.1 Inspections, 4.2 Certifications, 4.3 Handover of documentation.
The most common mistakes
- Too much detail: hundreds of items nobody updates.
- Too little: a single “works” item that says nothing.
- Forgetting indirect activities such as meetings, site visits and documentation.
- Not linking hours and purchases to the packages, losing the comparison with the budget.